Page
2.......... Environmental Monitoring and Audit
3.......... implementation status on the environmental
protection requirements
List
of Tables
Table 1.1 Summary of
Awarded Works Contracts
Table 2.1 Summary of Major
Construction Activities in the Reporting Period
Table 2.2 Summary of 1-Hour TSP Monitoring
Results in the Reporting Period
Table 2.3 Summary of
Construction Noise Monitoring Results in the Reporting Period
Table 3.1 Summary of EP
Submissions Status
List of Appendices
Appendix A Monthly
EM&A Report for August 2023 – Contract 1201 Tung Chung
West Station and Tunnels
Table 1.1 Summary of Awarded Works Contracts
|
Works Contract |
Description |
Construction
Start Date |
Contractor |
Environmental
Team |
|
1201 |
Tung Chung West Station and Tunnels |
June 2023 |
Bouygues – Dragages
(1201) JV |
AECOM Asia Co. Ltd. |
|
1202 |
Tung Chung East Station and Associated
Enabling Works for Track Diversions |
July 2023 |
Paul Y. – CRCC (TUE1202) JV |
Acuity Sustainability Consulting Limited |
Table 2.1 Summary
of Major Construction Activities in the Reporting Period
|
Works Contract |
Site |
Construction Activities |
|
1201 |
Tung Chung West
(TCW) Area |
·
Tree felling and transplantation ·
Covered walkway footing and erection ·
Footbridge ramp demolition ·
Site clearance, pre-drilling works and site
formation |
|
Tung Chung Cresecent (TCC) and Tung Chung Ancillary Building (TCA)
Areas |
·
Site clearance and tree felling ·
Ground investigation and predrilling ·
Hoarding installation ·
Storm drainage and sewerage diversion and
installation ·
Underground utilities investigation |
|
|
Barging Facility
Area |
· Concrete footing fabrication |
|
|
1202 |
Tung Chung East (TCE) Area |
·
Instrumentation
works ·
Site
clearance and predrilling works ·
Hoarding
& Shelter of Car Park works ·
Underground utilities installation for site office |
|
Area 138 |
·
Concrete
paving ·
Drainage
construction ·
Fencing
work |
Table 2.2 Summary
of 1-Hour TSP Monitoring Results in the Reporting Period
|
Monitoring Station ID |
Location |
TSP Concentration
(µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Exceedance due to the Project Construction (Yes/No) |
|
Works Contract 1201 |
|||||
|
DM-2 |
Sheraton Hong Kong Tung Chung Hotel Shopping Mall |
N/A(1) |
326 |
500 |
No |
|
DM-3 |
Shops at Tung Chung Crescent |
N/A(1) |
327 |
500 |
No |
|
DM-4 |
Yat Tung Shopping Centre |
6.3 – 91.8 |
312 |
500 |
No |
|
DM-5b(2) |
Ma
Wan Chung Village |
5.1 – 96.2 |
333 |
500 |
No |
|
Works Contract
1202 |
|||||
|
DM-1b(3) |
G/F
of Ying Yuet House |
19.9 – 154.9 |
327 |
500 |
No |
|
DM-1a |
TCNTE East - Planned Commercial Development (COM-1/Area 57) |
N/A(1) |
342 |
500 |
No |
Note:
(1)
Imapct monitoring to be
carried out during the construction period of corresponding activity
(2)
Alternative monitoring location to DM-5 Ma Wan
Chung Vilage in the approved EM&A Mnaual
(3)
Alternative monitoring location to DM-1 Rosita Yuen
Kindergarten in the appvoed EM&A Manual
Table 2.3 Summary
of Construction Noise Monitoring Results in the Reporting Period
|
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project Construction (Yes/No) |
|
Works Contract 1201 |
||||
|
NM2 |
Tung Chung Crescent |
N/A(1) |
75 |
No |
|
NM3a(3) |
2/F rooftop of Yat Tung Shoppgin Centre |
60.9 – 63.8 |
75 |
No |
|
Works Contract 1202 |
||||
|
NM1 |
Ying Tung Estate |
Below baseline level – 64.4 |
75 |
No |
|
NM4 |
Tung Chung Area 113 |
N/A(2) |
75 |
No |
|
NM6 |
Tung Chung Area 100 |
N/A(2) |
75 |
No |
Note:
(1)
Impact noise monitoring to be carried out during
the construction period of the corresponding activity
(2)
Impact noise monitoring to be carried out upon the
intake of the population and during the construction period of the
corresponding activity
(3)
Alternative monitoring location to NM3 Yat Tung
Estate in approved EM&A Manual
Table 2.4 Log
for Environmental Complaints, Notification of Summons and Successful
Prosecutions for the Reporting Month
|
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
|
1201 |
6 |
0 |
0 |
|
1202 |
0 |
0 |
0 |
Table 3.1 Summary
of EP Submissions Status
|
EP Condition (EP-614/2022) |
Submission |
Submission date |
|
Condition 1.12 |
Notification of
Commencement Date of Construction |
9
Mar 2023 9
May 2023 (update) |
|
Condition 1.14 |
Notification of
Commencement Date of Operation |
No
later than 1 month prior to the commencement of operation |
|
Condition 2.9 |
Notification of Setup of Community Liaison
Group |
21
Mar 2023 |
|
Condition 2.10 |
Construction Works Phasing
Schedule |
14
Apr 2023 |
|
Condition 2.11 |
EP Submission Schedule |
14
Apr 2023 |
|
Condition 2.12 |
Management Organization |
28
Apr 2023 |
|
Condition 2.13 |
Construction Noise Management
Plan (CNMP) ·
Works Contract No. 1201 ·
Works Contract No. 1202 |
10
Mar 2023 31
May 2023 (approval) 29
Aug 2023 (update) 10
Mar 2023 27
Jun 2023 (approval) |
|
Condition 2.14 |
Rail Noise Mitigation Plan
(RNMP) |
13
Jan 2023 25
Aug 2023 |
|
Condition 2.15 |
Plan on Noise Enclsoure at Tung Chung Crescent |
13
Apr 2023 29
Aug 2023 |
|
Condition 2.16 |
Compensatory Tree Planting
Implementation Plan |
To
be submitted at least 2 months before the commencement of the compensatory
tree planting |
|
Condition 2.17 |
Landscape and Visual Mitigatin Plan (LVMP) |
12
Apr 2023 |
|
Condition 2.18 |
Contingency and Response
Plan |
To
be submitted at least 2 months before the commencement of relevant part of
the construction works |
|
Condition 2.19 |
Wastewater Management Plan
(WWMP) |
9
Mar 2023 29
May 2023 (approval) |
|
Condition 2.20 |
Waste Management Plan
(WMP) |
16
Feb 2023 |
|
Condition 2.23 |
Futher Archaeological
Testing Report |
28
Sep 2022 |
|
Condition 2.25 |
Fixed Plant Noise Audit
Report |
To
be submitted at least 1 month before commencement of operation of the Project |
|
Condition 3.3 |
Baseline Monitoring Report |
28
Apr 2023 |
|
Condition 3.4 |
Monthly EM&A Report
No.1 to 2 Monthly EM&A Report
No.3 |
Reported
in previous Monthly EM&A Reports This
submission |
|
Condition 4.2 |
Dedicated Internet Website |
10
Jul 2023 |
Appendix A
Monthly EM&A Report
for
Contract
1201
Tung
Chung West Station and Tunnels
(August
2023)
Appendix B
Monthly EM&A Report
for
Contract
1202
Tung
Chung East Station and Associated Enabling Works for Track Diversions
(August
2023)