Table of Contents
2......... Environmental Monitoring and Audit
3......... implementation status on the environmental protection requirements
List of Tables
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Major Construction Activities in the Reporting Period
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
Table 3.1 Summary of EP Submissions Status
List of Appendices
Table 1.1 Summary of Awarded Works Contracts
|
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
|
1701 |
Oyster Bay Station and Associated Works |
April 2024 |
China State Construction Engineering (HK) Ltd. |
Aurecon Hong Kong Ltd. |
|
1731 [1] |
Trial Piles and Site Formation for Siu Ho Wan Depot Property Development – Phase 1 |
January 2023 |
Gammon Construction Ltd. |
WSP (Asia) Ltd. |
|
1732 [1] |
Cable bridges and associated civil works for cable diversion |
December 2021 |
Paul Y – CRCCI JV |
Acuity Sustainability Consulting Ltd. |
|
1733 [1] |
Vehicular Access Bridge, Demolition of Paint Shop and Construction of EV Stabling Tracks |
April 2022 |
Build King Civil Engineering Ltd. |
SGS Hong Kong Ltd. |
Note:
[1] The construction works for Works Contracts 1731, 1732 and 1733 were substantially completed in October 2024.
Table 2.1 Summary of Major Construction Activities in the Reporting Period
|
Works Contract |
Site |
Construction Activities |
|
1701 |
Overall |
· Site clearance, UU diversion, ABWF and BS works, drainage and road work and track works; · Bored pile, predrill and pre-bored H pile, precautionary sheet pile and ELS works; and · RP fencing installation, trial grouting works. |
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
|
Monitoring Station ID |
Location |
TSP Concentration (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Exceedance due to the Project Construction (Yes/No) |
|
Works Contract 1701 |
|||||
|
DM1 |
Siu Ho Wan Government Maintenance Depot |
2.0 – 22.0 |
294.7 |
500 |
No |
Table 2.3 Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month
|
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
|
1701 |
1 |
0 |
0 |
Table 2.4 Summary of Major Construction Activities in the Next Three Reporting Months
|
Works Contract |
Site |
Construction Activities |
|
1701 |
Overall |
· UU diversion, survey, trial pit, launching shaft mobilization works, typhoon door construction and installation · Precautionary sheet pile, pipe pile, bored pile, pre-bored H piles, resume mini pile, ELS for pile caps, pad footings, pile caps and ground beams construction works · Construction level crossing, RP fencing, pre-grouting, trial grouting works, OHL construction and track works, and PBSHP installation |
Table 3.1 Summary of EP Submissions Status
|
(EP-588/2021) |
Submission |
Submission date |
|
Condition 1.12 |
Commencement Date of Construction |
11 Jun 2021 (1st submission) 12 Jul 2021 (2nd submission) 12 Aug 2021 (3rd submission) |
|
Condition 1.14 |
Commencement Date of Operation |
No later than 3 months before commencement of operation |
|
Condition 2.7 |
Construction Works Phasing Schedule Proposal |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 29 Dec 2021 (Deposited) 9 October 2023 (1st Submission with updated Phase 1 works) 30 Nov 2023 (Deposited) |
|
Condition 2.8 |
Environmental Permit Submission Schedule |
12 Aug 2021 10 Sep 2021 (Deposited) 16 May 2025 (Updated) |
|
Condition 2.9 |
Management Organization |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 21 Mar 2022 (3rd Submission) 9 Aug 2022 (4th Submission) 16 Nov 2022 (5th Submission) 18 Sep 2023 (6th submission) 22 Jan 2024 (7th Submission) 21 Mar 2025 (8th Submission) |
|
Condition 2.10 |
Construction Noise Mitigation Plan |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 28 Dec 2021 (Deposited) 29 Mar 2023 (2nd Submission which covered Phase 1 main works) 18 May 2023 (3rd Submission which covered Phase 1 main works) 28 Jul 2023 (4th Submission for Phase 1 works) 30 Oct 2023 (5th Submission for Phase 1 works) 6 Dec 2023 (6th Submission for Phase 1 works) 8 Dec 2023 (Deposited) 21 Jun 2024 (7th Submission for Phase 1 works) 14 Feb 2025 (8th Submission for Phase 1 works) 9 Sep 2025 (9th Submission for Phase 1 works) |
|
Condition 2.11 |
Noise Mitigation Plan |
31 Mar 2023 (1st submission) 31 Jul 2023 (2nd submission) 20 Oct 2023 (3rd submission) 7 Mar 2024 (4th submission) 18 Mar 2024 (Approved) |
|
Condition 2.12 |
Fixed Plant Noise Audit Report |
To be submitted at least 1 month before commencement of operation of certain phase of the replanned SHD |
|
Condition 2.13 |
Waste Management Plan |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 28 Dec 2021 (Deposited) 30 Jun 2023 (1st Submission for Phase 1 work) 1 Aug 2023 (2nd Submission for Phase 1 works) 31 Aug 2023 (Deposited for Phase 1 works) |
|
Condition 2.14 |
Updated Contamination Assessment Plan |
To be submitted no later than 2 months before the commencement of site investigation works at the contaminated areas identified in the approved EIA report [1] |
|
Condition 2.15 |
Landscape and Visual Plan(s) |
27 Apr 2023 (1st Submission) 27 Jul 2023 (2nd Submission) 20 Oct 2023 (3rd Submission) 8 Dec 2023 (Approved) |
|
Condition 3.3 |
Baseline Monitoring Report |
1 Nov 2021 16 Nov 2021 (Deposited) |
|
Condition 3.4 |
Monthly EM&A Report No. 46 (September 2025) |
Submitted within 10 working days after the end of the reporting month |
|
Condition 4.2 |
Dedicated Internet Website |
12 Jan 2022 25 Jul 2023 (update address) 14 Mar 2024 (update address) |
Note:
[1] EPD acknowledged that Phase 1 works of the Project will not disturb/encroach into potential land contamination areas identified in the approved EIA Report on 6 May 2025.
Monthly EM&A Report for October 2025
Oyster Bay Station and Associated Works Contract 1701