Page
2......... Environmental
Monitoring and Audit
3......... implementation
status on the environmental protection requirements
List
of Tables
Table 1.1 Summary of
Awarded Works Contracts
Table 2.1 Summary of Major
Construction Activities in the Reporting Period
Table 2.2 Summary of 1-Hour TSP Monitoring
Results in the Reporting Period
Table 3.1 Summary of EP
Submissions Status
List of Appendices
Table 1.1 Summary of Awarded Works Contracts
|
Works Contract |
Description |
Construction
Start Date |
Contractor |
Environmental
Team |
|
1731 |
Trial Piles and Site Formation for Siu Ho Wan Depot Property
Development ¡V Phase 1 |
January 2023 |
Gammon Construction Ltd. |
WSP (Asia) Ltd. |
|
1732 |
Cable bridges and associated civil works for cable diversion |
December 2021 |
Paul Y ¡V CRCCI JV |
Acuity Sustainability Consulting Ltd. |
|
1733 |
Vehicular Access Bridge, Demolition of Paint Shop and Construction of
EV Stabling Tracks |
April 2022 |
Build King Civil Engineering Ltd. |
SGS Hong Kong Ltd. |
Table 2.1 Summary
of Major Construction Activities in the Reporting Period
|
Works Contract |
Site |
Construction Activities |
|
1731 |
Overall |
¡P
Site Clearance & Hoarding ¡P
Pre-drilling Works ¡P
Bored Piling Works |
|
1732 |
Overall |
¡P
General survey works ¡P
Instrumentation monitoring ¡P
Draw pits, cable ducts and cable trough works ¡P
EVA construction and watermain installation
near AB23 ¡P
Other EI works ¡P
Additional civil provisions for standalone
CCTV monitoring for EVA at east level crossing |
|
1733 |
Overall |
¡P
North side Bridge Footing Constructions ¡P
Mid Span Bridge Footing Constructions ¡P
Bridge Erection - Southern Side ¡P
EV Stabling line construction ¡P
Water Main Diversions - Northern Side |
Table 2.2 Summary
of 1-Hour TSP Monitoring Results in the Reporting Period
|
Monitoring Station ID |
Location |
TSP Concentration
(µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Exceedance due to the Project Construction (Yes/No) |
|
Works Contract 1731, 1732
& 1733 |
|||||
|
DM1 |
Siu Ho Wan Government Maintenance Depot |
60.4 ¡V 68.8 |
294.7 |
500 |
No |
Table
2.3 Log
for Environmental Complaints, Notification of Summons and Successful
Prosecutions for the Reporting Month
|
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
|
1731 |
0 |
0 |
0 |
|
1732 |
0 |
0 |
0 |
|
1733 |
0 |
0 |
0 |
Table 3.1 Summary
of EP Submissions Status
|
(EP-588/2021) |
Submission |
Submission date |
|
Condition 1.12 |
Commencement Date of Construction |
11 Jun 2021 (1st submission) 12 Jul 2021 (2nd submission) 12 Aug 2021 (3rd
submission) |
|
Condition 2.7 |
Construction Works Phasing Schedule Proposal |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 29 Dec 2021 (Deposited) |
|
Condition 2.8 |
Environmental Permit Submission Schedule |
12 Aug 2021 10 Sep 2021 (Deposited) |
|
Condition 2.9 |
Management Organization |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 21 Mar 2022 (3rd Submission) 9 Aug 2022 (4th Submission) 16 Nov 2022 (5th
Submission) 18 Sep 2023 (6th submission) |
|
Condition 2.10 |
Construction Noise Mitigation Plan |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 28 Dec 2021 (Deposited) 29 Mar 2023 (2nd Submission
which covered Phase 1 main works) 18 May 2023 (3rd Submission
which covered Phase 1 main works) 28 Jul 2023 (4th
submission for Phase 1 works) |
|
Condition 2.11 |
Noise Mitigation Plan |
31 Mar 2023 (1st submission) 31 Jul 2023 (2nd submission) |
|
Condition 2.13 |
Waste Management Plan |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 28 Dec 2021 (Deposited) 30 Jun 2023 (1st submission for Phase 1 work) 1 Aug 2023 (2nd submission for Phase 1 works) 31 Aug 2023 (Deposited for Phase 1 works) |
|
Condition 2.15 |
Landscape and Visual Plan(s) |
27 Apr 2023 (1st submission) 27 Jul 2023 (2nd submission) |
|
Condition 3.3 |
Baseline Monitoring Report |
1 Nov 2021 16 Nov 2021 (Deposited) |
|
Condition 3.4 |
Monthly EM&A Report No.21 (August 2023) |
Submitted within 10 working days after the
end of the reporting month |
|
Condition 4.2 |
Dedicated Internet Website |
12 Jan 2022 25 Jul 2023 (update address) |