Table of Contents
Page
2.......... Environmental Monitoring and Audit
3.......... implementation status on the environmental protection requirements
List of Tables
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Major Construction Activities in the Reporting Period
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
Table 3.1 Summary of EP Submissions Status
List of Appendices
Table 1.1 Summary of Awarded Works Contracts
|
Works Contract |
Description |
Construction Start Date |
Contractor |
Environmental Team |
|
1731 |
Trial Piles and Site Formation for Siu Ho Wan Depot Property Development – Phase 1 |
January 2023 |
Gammon Construction Ltd. |
WSP (Asia) Ltd. |
|
1732 |
Cable bridges and associated civil works for cable diversion |
December 2021 |
Paul Y – CRCCI JV |
Acuity Sustainability Consulting Ltd. |
|
1733 |
Vehicular Access Bridge, Demolition of Paint Shop and Construction of EV Stabling Tracks |
April 2022 |
Build King Civil Engineering Ltd. |
SGS Hong Kong Ltd. |
Table 2.1 Summary of Major Construction Activities in the Reporting Period
|
Works Contract |
Site |
Construction Activities |
|
1731 |
Overall |
· Site Clearance & Hoarding · Trial pits |
|
1732
|
Overall |
· General Survey Works ; · Instrumentation Monitoring ; · Civil Works for Cable and Watermain Diversion Stage 2a & 2b ; · AB11 Modification Works ; · Cable Brackets Construction along Trackside ; · Footings 1 & 2 for Link Bridge Construction ; · Pier and Truss Installation for the Cable Bridges ; · Trial Pits Digging ; and · Draw Pits, Ducting and Cable Trough Installation. |
|
1733 |
Overall |
· Paint Shop Demolition ; · Excavation ; · Substructure ; · Instruments Installation & Plate Load Test ; · EV Tracks – Formation and Track Installation ; · UU Diversion ; and · Installation of Piezometer and Standpipe. |
Table 2.2 Summary of 1-Hour TSP Monitoring Results in the Reporting Period
|
Monitoring Station ID |
Location |
TSP Concentration (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Exceedance due to the Project Construction (Yes/No) |
|
Works Contract 1732 & 1733 |
|||||
|
DM1 |
Siu Ho Wan Government Maintenance Depot |
59.5 – 66.0 |
294.7 |
500 |
No |
Table 2.3 Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month
|
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
|
1731 |
0 |
0 |
0 |
|
1732 |
0 |
0 |
0 |
|
1733 |
0 |
0 |
0 |
Table 3.1 Summary of EP Submissions Status
|
(EP-588/2021) |
Submission |
Submission date |
|
Condition 1.12 |
Commencement Date of Construction |
11 Jun 2021 (1st submission) 12 Jul 2021 (2nd submission) 12 Aug 2021 (3rd submission) |
|
Condition 2.7 |
Construction Works Phasing Schedule Proposal |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 29 Dec 2021 (Deposited) |
|
Condition 2.8 |
Environmental Permit Submission Schedule |
12 Aug 2021 10 Sep 2021 (Deposited) |
|
Condition 2.9 |
Management Organization |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 21 Mar 2022 (3rd Submission) 9 Aug 2022 (4th Submission) 16 Nov 2022 (5th Submission) |
|
Condition 2.10 |
Construction Noise Mitigation Plan |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 28 Dec 2021 (Deposited) |
|
Condition 2.13 |
Waste Management Plan |
1 Nov 2021 (1st Submission) 20 Dec 2021 (2nd Submission) 28 Dec 2021 (Deposited) |
|
Condition 3.3 |
Baseline Monitoring Report |
1 Nov 2021 16 Nov 2021 (Deposited) |
|
Condition 3.4 |
Monthly EM&A Report No.13 (Dec 2022) |
12 January 2023 |
|
Condition 4.2 |
Dedicated Internet Website |
12 Jan 2022 |